Liverpool Women’s Health Centre Building Project

The building project has been made possible through a grant provided by the Community Building Partnership program & is an exciting milestone in the Liverpool Women’s Health Centre history of providing quality health services to the women of Liverpool for the past 35 years.
The first floor addition has
- Addressed the cramped staff work space by the expansion of staff office areas and a dedicated manager’s office. Office space can also be utilized by increasing student placement requests e.g. TAFE, social work, arts and medicine.
- Provided the addition of two interview rooms to be used for counselling and assessment of crisis and walk-in clients.
- Provided an additional group/training room that will expand available group room space to three rooms creating additional opportunities, for example to work in partnership with community partners particularly SSWAHS Bi-lingual Community Educators, NSW Refugee Health, Liverpool Migrant Resource Centre in meeting the specific needs of refugee and newly arrived migrant women.
The centre has easy access for everyone in accordance with the Disability Discrimination Act 1992. The organisation endeavours to install a lift within the centre to allow access for disabled and less mobile clients and staff between first and ground floor.
At this stage, we have not been able to secure funding for the installation of a lift. All services and activities will be offered on the ground floor so that no person with walking difficulties or sensory impairments, wheelchair users and people with young children will be disadvantaged.
View the building progress updates
07 December 2010 Project completed
07 December 2010 Installation of blinds first floor completed

15 November 2010 Refurbishment of counselling rooms completed

15 November 2010 Refurbishment group room completed

12 November 2010 Carpet installation first floor completed

28 October 2010 Cement rendering ground floor completed

28 October 2010 Painting & detailing completed

12 October 2010 Lights, exit signs and smoke alarms installed

12 October 2010 Fit out WC completed

12 October 2010 Stairs painted

29 September 2010 – Cement rendering of first floor additions completed

29 September 2010 – Group room kitchenette installed

29 September 2010 – Office area painting of ceilings completed

22 September 2010 – Stairs installed

13 September 2010 – Insulation and internal linings completed

24 August 2010 – Cement rendering underway
12 August 2010 – Roof tiling completed

12 August 2010 – Installation of air conditioning underway

12 August 2010 – Installation of windows completed

30 July 2010 – Erection of internal walls

30 July 2010 – Roof tiling underway

16 July 2010 – Erection of wall & roof framing

05 July 2010 – Laying of 1st floor joists

05 July 2010 – Alteration for proposed stairs to first floor

10 June 2010 – Development Proposal

10 May 2010 – Liverpool Women’s Health Centre